The entry fee comes out of the budget£10.00 suggested

£8.39 to break even over 420 entries.

  1. Fixed costs 3850.00.
  2. Per-entry costs 1.80 × 420 entries = 756.00.
  3. Per-dancer costs 1.90 × 160 dancers = 304.00.
  4. Total cost 4910.00, less 1390.00 of other income, leaves 3520.00 to raise from entries.
  5. Over 420 entries that is 8.39 to break even.
  6. Adding a 500.00 surplus target and rounding up to the next 0.50 gives 10.00.

The working is returned, not just the number. A treasurer has to defend this to a committee that will ask where it came from, and “the system said £7.50” is not an answer. Rounded up, never down: a fee rounded down turns a budgeted surplus into a shortfall nobody notices per entry.

The committee charged £7.50

Both are kept. Next year wants to know what was charged and what would have covered it — which is why the P&L below is the specification for the budget after this one.

What happens at a smaller fieldBreak even at 495 entries. Below that the event loses money.

TurnoutEntriesIncomeCostSurplus
-30%294£3595.00£4592.00−£997.00
-15%357£4067.50£4751.00−£683.50
As expected420£4540.00£4910.00−£370.00
+15%483£5012.50£5069.00−£56.50

The question nobody asks until it is too late. Fixed costs do not shrink when forty dancers stay home, so a hall costs the same for eighty as for four hundred and medals do not — which is why a cost line carries a behaviour and not just an amount. Getting this wrong is how a committee loses money on a sold-out event.

Trophies, against the lead timeover budget

A reminder that fires late is a feis with no trophies. The order-by date is derived from the supplier’s lead time and the event date, never stored — a feis that moves takes its deadlines with it, and a stored date is the one that goes stale in silence. An accepted quote counts as money spent, because a treasurer who only counts placed orders finds the overspend after it is unfixable.

The governing body will invoice£438.75

Per-dancer levyAn Coimisiún160 dancers at 1.50 each£240.00
Annual affiliationAn CoimisiúnFlat fee per event£120.00
Regional levyRegional council2.50% of 3150.00 entry income£78.75

Every body charges something and none of them charge it the same way. The working is kept because the invoice will not match unless the basis matches.

Counting the cash£5.00

745.00 in cash against 740.00 expected, most of it in the door tin.

TinCountedFloatTakingsExpectedVariance
door£455.00£50.00£405.00£380.00£25.00
programme£120.00£20.00£100.00£120.00−£20.00
vendor£240.00£0.00£240.00£240.00—

Counted by denomination, not as a total: somebody with a float bag counts notes into piles, and asking for one number makes them do arithmetic they will get wrong and makes a miscount impossible to find. The float comes out before anything reconciles — the commonest “we are £50 down” at a feis is a float nobody subtracted. A variance is a number with a reason next to it, never an error: cash events run one every time, and a screen that treats it as a fault gets a fake number typed into it.

Profit and loss−£899.80

Loss of 899.80 against a budgeted loss of 282.80.

Where the difference came from

Costs

LineBudgetedActualVariance
Ulster Hall, one day£1420.00£1420.00£0.00
Three adjudicators, fees and travel£960.00£1045.00£85.00
Two musicians£360.00£360.00£0.00
Perpetual cups and shields£510.00£510.00£0.00
Public liability£180.00£180.00£0.00
Programmes and signage£420.00£478.00£58.00
MedalsRestated at 380 entries.£684.00£684.00£0.00
Number cardsRestated at 152 dancers.£60.80£60.80£0.00
Governing-body levyRestated at 152 dancers.£228.00£228.00£0.00
Total£4822.80£4965.80£143.00

Per-entry lines are restated at the turnout that actually happened — 380 entries and 152 dancers, not the 420 and 160 budgeted. A committee that got fewer dancers did not overspend on medals by getting them, and a P&L that says it did sends them looking for a saving that was never available. This is the one arithmetic decision a spreadsheet usually gets wrong.

Does it tie back to money that moved?

Card and cash checked separately. Netting them hides which half a discrepancy is in, and they have completely different explanations: a card variance is a settlement timing question, a cash variance is a tin somebody has not handed in.

Year on year

YearEntriesSurplusPer entry
Belfast Feis 2024340£320.00£0.94
Belfast Feis 2025365£410.00£1.12
Belfast Feis 2026380£100.20£0.26

Surplus per entry has fallen by 0.68 since 2024, from 0.94 to 0.26. Surplus per entry is the comparable number: an event that grew by a hundred entries and made the same money got worse, and a total hides that completely.

Sponsorship400.00 agreed of 650.00, 250.00 short, with 100.00 still out for an answer.

Offers are counted separately from what is agreed. A committee that budgets on offers is a committee that budgets on hope, and the budget above reads the agreed figure.

The fulfilment report1 outstanding

Byrne Motors was named from the stage 9 times during Belfast Feis 2026, alongside 3 other placements.

PromisedDeliveredEvidence
Named from the stage, six timesmc mention9 of 69 sponsor announcements naming Byrne Motors were read from the stage.
Half page, inside back coverprogramme ad1 of 1Proof programme-p7.pdf signed off on 2026-02-28.
The Byrne Motors Perpetual Cupaward naming11 award carrying Byrne Motors’s name was presented.
Banner behind stage 1banner0No record of this being delivered.

This is what renews a sponsorship, and no spreadsheet-based committee can produce it. The counts come from what the platform recorded happening — announcements actually read, awards actually presented, proofs actually approved — never from the agreement. A report restating what was promised proves nothing, and a sponsor can tell the difference immediately. Shortfalls are in the report: hiding one is how a sponsor finds out from somebody else and does not renew.